Tattershall Castle Group
Project -Hop Poles, Hammersmith
Project type: Pub
Project Management: PSE Associates
Quantity Surveyor: PSE Associates
Contractor: Manad
Commencement Date: 3rd September 2007
Completion Date: 15th October 2007
Duration: 8 weeks on site
Summary:
Internal and external refurbishment of existing ground floor configuration, and formation of function room, bar and terraceon the first floor.